Week of May 21

- Contractor to continue excavation and backfill of new storm sewer lines
- Contractor will be backfilling the current excavation located between O’Neil parking lots, St. Rita’s, & Carney Hall
- Contractor will continue preparations for power changeover on 5/25
- Installation of additional foundational support (underpinning) at the former Carney tower location, which involves excavation & concrete pours in the tower footprint
- Portions of the lowest parking lot will be blocked off while excavating for the new storm pipe & manholes. Please be aware of workers, cones, & traffic signs.