Week of July 16

- Contractor will continue removal of materials in Sullivan Hall
- Complete demolition of Sullivan stairs, elevator shaft, & mechanical room
- Install underground storm water basin in upper parking lot next to O’Neill Center.
- Begin excavation in courtyard area between Sullivan, Carney, Good Council, & Duffy Halls.
- Continue installation of new sprinkler system in Carney Hall
- Excavate and prepare foundation for new elevator shaft at Carney Hall
- Continue re-piping chilled water loops in Carney Hall for Air Conditioning unit
- Power will be provided to relocated Air Conditioning unit
- Install waterproofing at Carney underpinning, exposed foundation