Week of August 20

- Begin excavation for foundations of the new building connecting Carney with Sullivan
- Complete waterproofing installation at Carney underpinning area
- Complete re-grading, curb installation, & paving of upper parking lots between O’Neil & football field
- Re-activation of Carney air conditioning unit
- Complete interior demolition of Sullivan Hall
- Complete interior demolition of Carney C106 classroom (new mechanical room)
- Relocate fence in courtyard area to prepare for upcoming school year