Week of September 17

- Contractor pouring concrete footers & footer walls at front of new CSI building
- Installation of waterproofing materials on poured footers
- Installation of insulation at new chilled water piping in Carney Hall
- Work on air conditioner system in Carney Hall
- Will Receive deliveries of steel materials on Tuesday
- Crane will arrive on site on Wednesday or Thursday (9/19-20) to begin setting steel (9/20-25)
- Adding stone to the storm basin area in front of Sullivan Hall